Grade 10 CSS Budget of Work Group 1
Grade 10 CSS Budget of Work Group 1
BUDGET OF WORK
FIRST QUARTER
CONTENTS
Types and parts of computers 3
Computer operating systems
Windows / MAC OS X /Linux
Peripheral devices
Computer systems design
Computer assembly procedures 2 June 3-4
Power ON self-test and basic-input- 5 June 6,7,10,11,13
output-system (BIOS) configuration
procedures 4 June 14, 17-19
CMOS 2 June 20,21
Motherboards 5 June 25-28 July 1
Multimedia storage devices: 1 July 2
- Video cards
- Sound cards
- Graphical user interface 2
2 July 3-4
2 July 5, 8
July 9-10
2 Aug 8-9
BUDGET OF WORK
SECOND QUARTER
Windows XP/7/8/10
Aug 27-29
3.4 Configure peripherals/ devices in accordance with 3 days
manufacturer’s instructions and/ or OS installation
procedures
Sept 16-27
3.5 Access OS and drivers’ updates/ patches in 10 days
accordance with manufacturer’s recommendations and
requirements
Checking of work
Oct. 7- 11
2. Application 5 days
Oct. 14-16
3. Checking of work 3 days
BUDGET OF WORK
THIRD QUARTER
CONTENT:
Computer network concepts
Network cable installation JAN 15-17,20-23
Copper cable splicing and cable testing JAN 24, 27-31
Fiber optic cables splicing and installation requirements Feb 3-7
Philippine Electrical Code relevant to data connection FEB 8-10,14
OHS standards and 5S principles
Practicing 3Rs (reduce, reuse, recycle/recover) FEB 17-19
3Rs environmental policies
Managing waste from electrical and electronic equipment FEB 20-21
(WEEE) FEB 24, 26-27
FEB 28, MAR 2-4
MAR 5-6, 9